Scotlandville Magnet High School Renovations
9870 Scotlandville Avenue, Baton Rouge, LA 70807

NEW Campus-Wide Features
The renovation will include a new main entry (semi-enclosed) and raised covered entries to the Auditorium and Gym. The chain link gates will be replaced with custom designed decorative entrance gates.
New landscaping will adorn the front and Quad area (between Classroom Buildings E and F) and the new covered walkway between the middle entrances to Classroom Buildings E and F, and the covered student congregational areas at the Main Entry and Cafeteria. The old auto shop building and wash rack will be removed.
Other Changes on the Entire Campus
New windows, doors, and door hardware (new keying system)
New ceilings and lighting, new water coolers
Paint all surfaces
New corridor and athletic lockers
New walkway covers
Clean and add-to existing storm drainage
New air conditioning piping; refurbish the existing ac units
New restroom fixtures, lighting, floors, toilet partitions, and ventilation
Re-stripe existing parking lots; create accessible parking; clean and seal existing brick
Auditorium Building
New Control Desk in Auditorium
New Stage curtain and wood flooring
New carpet at Auditorium Seating aisles
New speaker system and stage lighting
Dance classroom addition with office, new closet for Drama and Choral
New Choral Practice Room and new choral acoustical treatment
New accessible wheelchair lift for Stage
New Band Ensemble room and new band acoustical treatment
Library & Media Center
New circulation desk and entrances
New carpet tile floor
New office and conference room
Renovate the (2) existing conference rooms and add windows to exterior
Creation of multimedia and computer area
New library furniture and shelving
Install projection screens and new water cooler
Administration Areas
Completely new floor plan with Addition
Five (5) new toilet rooms
Health/Nurse office with Exam Room and toilet
Attendance Office and Attendance Reception
Three (3) assistant principal offices
Conference Room
Mail Room
Workroom and Mailroom
Two (2) storage closets and new telecommunication room
Gymnasium
10,000 sf addition: public restrooms, practice gym, Weight Room, Classroom/Conference Room
Air-condition existing gym and locker rooms
Re-finish and repair existing gym floor; re-stripe to accommodate competition volleyball
Refurbish existing goals, install electric winches; new protective pads
New sound system and lighting and new acoustical treatment at existing Gym
New state-of-the-art retractable bleachers (electric)
Refurbish the trophy case, concession, lobby
New Training Room, Laundry Room, Female Team Locker Room
New epoxy floors at all locker and restroom areas
All locker rooms to be totally renovated and ventilated
Classroom Building “E” & “F”
ADA Limited Use elevators to be installed
New Teachers’ Centers with Toilet Rooms
New Teacher storage cabinets and classroom specialties
New Supply closets (two at each building)
New stair railings
Remove high windows and complete enclosure of corridors resulting in sound attenuation
Building E: New Kiln Room
Building F: New Governmental Affairs Wing with Multipurpose Room, Editing Room, Supply Closets
Building F: (4) Science Classroom renovations
Cafeteria
Renovate Student Dining and Faculty Dining areas
Creation of Vending Room
New student wash basins
New ceiling and lighting installation at Dining and Kitchen
Restore and renovate Service Room for Kitchen
New concrete paving and parking between Cafeteria and Technology Building
Technology Classroom Building
Extended Covered Walk to Engineering Lab
New floor at Engineering Lab
New classroom specialties
Football Stadium Building
New athletic lockers with integral benches
New Training Room
Renovate Snack Stand, Public Restrooms, and Laundry Room
Extend walkway cover to Boys Locker Room
New Girls Athletic Coach Office
Football and Track & Field Area
New Press Box, Speaker and Sound System, Field Lighting, new chain link fence and railings
New aluminum seating at Home Side, new Visitor Seating, new ADA ramps and seating
Renovate existing Home Ticket Booth, new Visitor Ticket Booth
New paved parking lot at Visitor Side
New track surface, new field event apparatus and surfaces
Central Plant
Addition to accommodate new chiller room
New insulation and louvers
Renovate office